SPOKANE VALLEY

8th Ave from McKinnon to Fancher – Closed through
mid-September for paving, striping and shoulder-work. Signs redirect traffic
via Carnahan, 16th and Bettman/Dickey.  

Sprague Ave from Vista to Herald – Reduced to two lanes westbound through early September for resurfacing, stormwater drainage improvements, and
sidewalk work.

Appleway Boulevard from Thierman to Park – Reduced to two lanes eastbound through early October for resurfacing, stormwater drainage improvements, and
sidewalk work. The new sidewalk on the south side of the road will be available
for pedestrian use for the remainder of the project.

Sprague Avenue between University and Pines – Closed Friday, September 19 from 6 p.m. to 10 p.m. for the Valleyfest Hearts of Gold parade.

SPOKANE CITY
Ruby from Desmet to Boone- One lane and sidewalk closed from Sept. 15-19 for demolition work.

Hawthorne and U.S. 2- Replacement of a damaged signal pole starts Tuesday, Sept. 16 at 8:30 a.m.
Work is expected to be completed by 3 p.m.  The signal will be placed in
red-red flash during this time. Both the northbound and westbound dedicated
right turn lanes will remain open, but the adjacent northbound and westbound
through-lane will be closed.  As a result, both the northbound and
westbound will have only one through lane open.

Main Sidewalk Closure-  The sidewalk on Main between Browne and Division will be closed until Sept.17 for sidewalk repairs.

Main Sidewalk Closure, Take 2– The sidewalk on Main and Howard and a traffic
lane on Main will be closed until Sept. 22 to replace sidewalks. 
Main Sidewalk Closure, Take 3- A section of sidewalk on Main between Wall St. and Post St. is closed until Sept. 27 to place dumpsters. 
Howard Street from 1st Ave. to railroad tracks-  Blocked for crane work at the Wells Fargo building.
Division Street Sidewalk Closure- The sidewalk closure at 1120 N. Division has
been extended until Sept. 30 for demolition work.
Grind and Overlay Project- Work has resumed on the Excell portion of
the project. This will be followed up with asphalt patching, along with
new curb and sidewalk construction. The project calls for
completion of grind and overlay repair on the following streets:
o   Pittsburg
Street from Heroy Avenue to Wellesley Avenue and Heroy Avenue from Helena
Street to Pittsburg Street. Work is substantially complete.
o   Arthur
Street from 13th Avenue to Newark Avenue (excluding 9th
Avenue west to 9th Avenue east)
o   Excell
Avenue from G Street to the beginning of the cul-de-sac east of Audubon Drive.
Removal work has begun.
East Sprague Lane Closure- One lane
will be open each direction on Sprague from Hatch to Scott Streets for construction of a combined sewer overflow
facility on City property across from the City’s Sewer Maintenance Facility.
Kendick Water Main Installation- Crews will replace an
8-inch water main in Kendick Avenue from approximately 1,200 feet west of Nine
Mile Road to Nine Mile road. Detour signage is in place on State Route 291. Current
residents will be allowed access to their property.
Greene St. Bridge Lane closure- Greene Street from Marshall
Avenue to Carlisle Avenue will be reduced to one lane each direction for six weeks. Carlisle at Greene will also be closed and a
detour in place. This project will pull a 24” pipe through
the existing 30” steel main suspended under the Greene Street Bridge. The new pipe will not add weight to the bridge due
to the smaller amount of water that will be flowing through the new pipe.
Lincoln/Monroe Intersection Construction- A new 4-way stop has been installed at 10th
and Madison to help with traffic in and out of Huckleberry’s Natural Market.
Crews expect to have the intersection at 14th and Lincoln open in
the coming weeks. The
project includes reconstruction of the street by replacing the asphalt
surfacing, including ADA ramps as needed. Lincoln/Monroe street will be closed
from 7th-17th Avenues. The closure is expected to last
through mid-October.
High Drive Construction- Roadway excavation and subgrade preparation are
nearly finished. Aggregate placement is beginning and curb and gutter will
follow.  This project includes pavement reconstruction, CSO storage facilities,
storm, sewer, swales, and water main replacement from 29th Avenue to
Bernard Street. Phase One construction is expected to last until mid-October.
Phase Two of this project, Bernard Street to Hatch Road will begin spring of
2015.
Community Development Sidewalk Project- Crews are working
in two neighborhoods: Logan and Emerson-Garfield.  All obstructions are
sidewalk related and are barricaded by the contractor.  All street
obstructions are minor due to moving equipment. This
project involves construction of concrete curb and sidewalk, concrete curb and
sidewalk removal.
Francis Ave. from Division to Crestline- Crews expect to finish
paving the north half of Francis within the week. Traffic is scheduled to be
flipped Sunday night while crews transition to the southern half.  This
project will rehabilitate Francis Avenue from Division to Crestline
Streets.  The work is curb to curb and includes installation of ADA curb
ramps, where needed. 
WSDOT
US 2/Espanola Road to Interstate 90- Between the hours of 7 p.m. and 6
a.m., Monday through Friday, expect intermittent lane closures
in the vicinity of Flint Rd. for highway resurfacing and the installation of a traffic signal system. Flint Road is closed from US 2 to the
south.  A detour is available.   
US 2/Airport Interchange Vicinity- Monday through Thursday, Sept.
15-18, from about 9 a.m. until as late as 3 p.m., be alert for
lane restrictions on US 2 in the vicinity of the airport interchange for bridge joint and deck repairs.  All
on and off ramps open.
I-90/Liberty Park to
Havana Street-
 Be alert for evening and overnight lane
and ramp closures for replacement of light poles.  
I-90/Vicinity of University Road- On Monday
and Tuesday, Sept. 15-16, from about 9 p.m. until as late as 6 a.m. the
following morning, westbound I-90 will be reduced to one through lane for repairs to message signs. Be alert for slow traffic, congestion, and delays.
SPOKANE COUNTY
Bruce Rd. Bridge- Closed for reconstruction. A detour is in place.
Country Homes Blvd.- The southbound lanes are closed from Cedar to Wall.
Translate (Traducir/Перевод) »